spective of the statute. This phrase was not effective to relieve the state from its duty to provide the site for the work. If it were so intended appropriate language could have been used. Our view is that neither this phrase, nor the legal obligation on the town to build the structure, if that obligation be conceded for the purpose of argument, relieved the state from its duty. The claimant had no relations with the town. The state, on the contrary, had ample opportunity to protect itself. It could have refrained from executing the contract until it had received the proper guaranties. The risk of the town's omission was on it, and not on the claimant. In addition, the state executed the contract, not only without assurances, but with full knowledge of the town's refusal, of which claimant was ignorant, and then compelled the claimant to begin the work. In Lane Brothers Co. v. State of New York, 11 State Dept. Rep. 117, the contract provided: "It is expected that the masonry abutments and superstructure necessary to carry the railroads over the canal prism together with so much of the excavation and backfilling as may be necessary therefor will be carried out by the railroad companies." The companies refused to do the work, the state failed to do it, the contractor thereby was denied the site for his operations and impeded, and Judge Haight, official referee, said: "It consequently follows that the State within a reasonable time was obligated to provide the contractor with the sites of the railroad companies, in order that it might perform its contract in excavating the prism of the canal thereunder. This the State has failed to do and, therefore, it became liable to the claimant for a breach of contract for the damage it has sustained by reason of such failure. "Under the provisions of the contract, as I have already shown, the State expected that the railroad companies would construct the bridges over the canal, but this the companies failed to do. It, therefore, becomes the duty of the State to either construct the bridges or let contracts therefor." A somewhat similar proposition was involved in Schunnemunk Construction Co. v. State of New York, 116 Misc. Rep. 770. In that case the county failed to acquire the necessary rights of way before construction began, as required by statute. The contractor thus was denied the site for his work and his progress delayed. We held the state liable, saying: "The issue is whether the state has violated the contract, by interfering with and interrupting the claimant in its performance of its obligation. Such interference between individuals or corporations confers a right of action. (Mansfield v. N. Y. Cent., etc., R. Co., 102 N. Y. 205; Del Genovese v. Third Ave. R. R. Co., 13 App. Div. 412; affd., 162 N. Y. 614.) * * "We are not unmindful of the statutory provisions. above referred to, but the claimant had no power or function in that connection. It was the duty of the county to procure the right of way, and of the state to satisfy itself in that respect before directing the claimant to proceed. This was a matter between the state and the county, and the state could use its own means to assure, protect and inform itself, before ordering claimant to begin work. No question of ignorance of law as an excuse is involved here." The only remaining question is one of fact. The absence of the culvert very seriously delayed and damaged the claimant. It was not reasonably possible, or practicable, for the claimant to move its shovel around the ravine in the winter of 1915-1916. That inquiry is of little importance, anyway. The claimant was entirely justified in keeping the shovel on the east side of the ravine, in position to resume work when the culvert was completed, relying as it did, and had a right to, upon the repeated assurances of the state that it soon would be in place. Claimant was not obliged to assume their assurances to be worthless and to expend the considerable sum and effort required to make the detour. We find, however, part of the damages for delay, for which recovery is sought, was not the result of the state's breach of the contract, but was the fault of the claimant. An award is made in the sum of $23,893.25, being the damages suffered by the claimant solely because of the state's default. ACKERSON, P. J., concurs. Ordered accordingly. INDEX. ABATEMENT. Of legacies. See Wills. ACCOMPLICE. See Criminal Procedure. ACCOUNTING. Testamentary trustee· ·Apportionment of extraordinary stock ACTIONS. When consolidation not ordered. See City Court of New York; Wills. ADEQUATE REMEDY AT LAW. ADVERSE POSSESSION. Action to Tenants in common Dower - Guardian in socage. See Eminent Domain. AGENCY. See Principal and Agent. AGREEMENT. To adopt week work system in place of piece work, etc. ALIMONY. See Contempt; Husband and Wife. ARREST. See Provisional Remedies. ATTACHMENT. See Contracts. AUTOMOBILES. See Contracts. BAIL. See Criminal Procedure. BAILMENT. Conversion-Involuntary bailee exercising dominion over article |