forces; or by an agent of any such government, power, authority, or forces; or (B) other peril, of type not listed above, if such other peril is customarily covered by insurance (or by a reserve for self-insurance) in accordance with the normal practice of the Contractor, or the prevailing practice in the industry in which the Contractor is engaged with respect to similar property in the same general locale.

The perils as set forth in (i) and (ii) above are hereinafter called "excepted perils."

'This clause shall not be construed as relieving a subcontractor from liability for loss or destruction of or damage to the Government-furnished Property while in his possession or control, except to the extent that the subcontract, with the prior approval of the Contracting Officer, may provide for the relief of the subcontractor from such liability. In the absence of such approval, the subcontract shall contain appropriate provisions requiring the return of all Governmentfurnished Property in as good condition as when received, except for reasonable wear and tear or for the utilization of the property in accordance with the provisions of the prime contract.

The term "Contractor's managerial personnel" as used herein means the Contractor's directors, officers, and any of his managers, superintendents, or other equivalent representatives who have supervision or direction of:

(1) All or substantially all of the Contractor's business;

(ii) All or substantially all of the Contractor's operation at any one plant or separate location at which the contract is being performed;

(iii) A separate and complete major industrial operation in connection with the performance of this contract.

(2) The Contractor represents that he is not including in the price hereunder, and agrees that he will not hereafter include in any price to the Government, any charge or reserve for insurance (including self-insurance funds or reserve) covering loss or destruction of or damage to the Governmentfurnished Property caused by any excepted peril.

(3) Upon the happening of loss or destruction of or damage to any Governmentfurnished Property caused by an excepted peril, the Contractor shall notify the Contracting Officer thereof, and shall communicate with the Loss and Salvage Organization, if any, now or hereafter designated by the Contracting Officer, and with the assistance of the Loss and Salvage Organization so designated (unless the Contracting Officer has directed that no such organization be employed), shall take all reasonable steps to protect the Government-furnished Property from further damage, separate the dam

aged and undamaged Government-furnished Property, put all the Government-furnished Property in the best possible order, and furnish to the Contracting Officer a statement of:

(1) The lost, destroyed, and damaged Government-furnished Property;

(ii) The time and origin of the loss, destruction, or damage;

(iii) All known interests in commingled property of which the Government-furnished Property is a part; and

(iv) The insurance, if any, covering any part of or interest in such commingled property.

The Contractor shall be reimbursed for the expenditures made by him in performing his obligations under this subparagraph (3) (including charges made to the Contractor by the Loss and Salvage Organization, except any of such charges the payment of which the Government has, at its option, assumed directly), to the extent approved by the Contracting Officer and set forth in a Supplemental Agreement.

(4) With the approval of the Contracting Officer after loss or destruction of or damage to Government-furnished Property, and subject to such conditions and limitations as may be imposed by the Contracting Officer, the Contractor may, in order to minimize the loss to the Government or in order to permit resumption of business or the like, sell for the account of the Government any item of Government-furnished Property which has been damaged beyond practicable repair, or which is so commingled or combined with property of others, including the Contractor, that separation is impracticable.

(5) Except to the extent of any loss or destruction of or damage to Governmentfurnished Property for which the Contractor is relieved of liability under the foregoing provisions of this clause, and except for reasonable wear and tear or depreciation, or the utilization of the Government-furnished Property in accordance with the provisions of this contract, the Government-furnished Property (other than property permitted to be sold) shall be returned to the Government in as good condition as when received by the Contractor in connection with this contract, or as repaired under paragraph (e) above.

(6) In the event the Contractor is reimbursed or compensated for any loss or destruction of or damage to the Governmentfurnished Property, caused by an excepted peril, he shall equitably reimburse the Government. The Contractor shall do nothing to prejudice the Government's rights to recover against third parties for any such loss, destruction, or damage and, upon the request of the Contracting Officer, shall at the Government's expense furnish to the Government all reasonable assistance and cooperation (including the prosecution of suit and

the execution of instruments of assignment in favor of the Government) in obtaining recovery. In addition, where a subcontractor has not been relieved from liability for any loss or destruction of or damage to the Government-furnished Property, the Contractor shall enforce the liability of the subcontractor for such loss or destruction of or damage to the Government-furnished Property for the benefit of the Government.

*(7) If this contract is for the development, production, modification, maintenance, or overhaul of aircraft, or otherwise involves the furnishing of aircraft by the Government, the "Ground and Flight Risk" clause of this contract shall control, to the extent it is applicable, in the case of loss or destruction of, or damage to, aircraft.

(g) The Government shall at all reasonable times have access to the premises wherein any Government-furnished Property is located.

(h) Upon the completion of this contract, or at such earlier dates as may be fixed by the Contracting Officer, the Contractor shall submit, in a form acceptable to the Contracting Officer, inventory schedules covering all items of Government-furnished Property not consumed in the performance of this contract (including any resulting scrap) or not theretofore delivered to the Government, and shall deliver or make such other disposal of such Government-furnished Property as may be directed or authorized by the Contracting Officer. The net proceeds of any such disposal shall be credited to the contract price or shall be paid in such other manner as the Contracting Officer may direct.

(i) Directions of the Contracting Officer and communications of the Contractor issued pursuant to this clause shall be in writing. § 18-13.503 Government property clause for cost-reimbursement type

contracts.

The following clause shall be used in cost-reimbursement type contracts for supplies and services (except contracts for experimental, developmental, or research work with educational or nonprofit institutions, where no profit to the contractor is contemplated) when NASA is to furnish to the contractor, or the contractor is to acquire for the account of the Government, material, special tooling, or industrial facilities.

GOVERNMENT PROPERTY (OCTOBER 1963) (a) The Government shall deliver to the Contractor, for use in connection with and

*This subparagraph may be omitted where it is clearly inapplicable and shall be deleted when the Ground and Flight Risk clause is omitted.

under the terms of this contract, the property described in the Schedule or specifications, together with such related data and information as the Contractor may request and as may reasonably be required for the intended use of such property (hereinafter referred to as "Government-furnished Property”). The delivery or performance dates for the supplies or services to be furnished by the Contractor under this contract are based upon the expectation that Government-furnished Property suitable for use will be delivered to the Contractor at the times stated in the Schedule or, if not so stated, in sufficient time to enable the Contractor to meet such delivery or performance dates. In the event that Government-furnished Property is not delivered to the Contractor by such time or times, the Contracting Officer shall, upon timely written request made by the Contractor, make a determination of the delay occasioned the Contractor and shall equitably adjust the estimated cost, fixed fee, or delivery or performance dates, or all of them, and any other contractual provisions affected by such delay, in accordance with the procedures provided for in the clause of this contract entitled "Changes." In the event that Government-furnished Property is received by the Contractor in a condition not suitable for the intended use, the Contractor shall, upon receipt thereof, notify the Contracting Officer of such fact and, as directed by the Contracting Officer, either (i) return such property at the Government's expense or otherwise dispose of the property or (ii) effect repairs or modifications. Upon completion of (i) or (ii) above, the Contracting Officer upon written request of the Contractor shall equitably adjust the estimated cost, fixed fee, or delivery or performance dates, or all of them, and any other contractual provision affected by the return or disposition, or the repair or modification, in accordance with the procedures provided for in the clause of this contract entitled "Changes." The foregoing provisions for adjustment are exclusive and the Government shall not be liable to suit for breach of contract by reason of any delay in delivery of Government-furnished Property or delivery of such property in a condition not suitable for its intended use.

(b) Title to all property furnished by the Government shall remain in the Government. Title to all property purchased by the Contractor, for the cost of which the Contractor is entitled to be reimbursed as a direct item of cost under this contract, shall pass to and vest in the Government upon delivery of such property by the vendor. Title to other property, the cost of which is reimbursable to the Contractor under the contract, shall pass to and vest in the Government upon (i) issuance for use of such property in the performance of this

contract, or (11) commencement of processing or use of such property in the performance of this contract, or (iii) reimbursement of the cost thereof by the Government, whichever first occurs. All Governmentfurnished Property, together with all property acquired by the Contractor title to which vests in the Government under this paragraph, is subject to the provisions of this clause and is hereinafter collectively referred to as "Government Property."

(c) Title to the Government Property shall not be affected by the incorporation or attachment thereof to any property not owned by the Government, nor shall such Government Property, or any part thereof, be or become a fixture or lose its identity as personalty by reason of affixation to any realty. The Contractor shall comply with the provisions of the NASA Industrial Property Control Manual (NPC-105) as in effect on the date of the contract, which Manual is hereby incorporated by reference and made a part of this contract.

(d) The Government Property provided or furnished pursuant to the terms of this contract shall, unless otherwise provided herein, be used only for the performance of this contract.

(e) The Contractor shall maintain and administer, in accordance with sound industrial practice, a program for the maintenance, repair, protection, and preservation of Government Property so as to assure its full availability and usefulness for the performance of this contract. The Contractor shall take all reasonable steps to comply with all appropriate directions or instructions which the Contracting Officer may prescribe as reasonably necessary for the protection of Government Property.

(f) (1) The Contractor shall not be liable for any loss of or damage to the Government Property, or for expenses incidental to such loss or damage, except that the Contractor shall be responsible for any such loss or damage (including expenses incidental thereto):

(i) Which results from willful misconduct or lack of good faith on the part of any one of the Contractor's directors or officers, or on the part of any of his managers, superintendents, or other equivalent representatives, who has supervision or direction of— (A) all or substantially all of the Contractor's business; or

(B) all or substantially all of the Contractor's operations at any one plant or separate location in which this contract is being performed, or

(C) a separate and complete major industrial operation in connection with the performance of this contract;

(ii) which results from a failure on the part of the Contractor, due to the willful misconduct or lack of good faith on the part of any of his directors, officers, or other rep

resentatives mentioned in subparagraph (1) above

(A) to maintain and administer, in accordance with sound industrial practice, the program for maintenance, repair, protection, and preservation of Government Property as required by paragraph (e) hereof; or

(B) to take all reasonable steps to comply with any appropriate written directions of the Contracting Officer under paragraph (e) hereof;

(iii) for which the Contractor is otherwise responsible under the express terms of the clause or clauses designated in the Schedule;

(iv) which results from a risk expressly required to be insured under this contract but only to the extent of the insurance so required to be procured and maintained, or to the extent of insurance actually procured and maintained, whichever is greater; or

(v) which results from a risk which in in fact covered by insurance or for which the Contractor is otherwise reimbursed, but only to the extent of such insurance or reimbursement;

Provided, That, if more than one of the above exceptions shall be applicable in any case, the Contractor's liability under any one exception shall not be limited by any other exception. This clause shall not be construed as relieving a subcontractor from liability for loss or destruction of or damage to Government Property in his possession or control, except to the extent that the subcontract, with the prior approval of the Contracting Officer, may provide for the relief of the subcontractor from such liability. In the absence of such approval, the subcontract shall contain appropriate provisions requiring the return of all Government Property in as good condition as when received, except for reasonable wear and tear or for the utilization of the property in accordance with the provisions of the prime contract.

(2) The Contractor shall not be reimbursed for, and shall not include as an item of overhead, the cost of insurance, or any provision for a reserve, covering the risk of loss of or damage to the Government Property, except to the extent that the Government may have required the Contractor to carry such insurance under any other provisions of this contract.

(3) Upon the happening of loss or destruction of or damage to the Government Property, the Contractor shall notify the Contracting Officer thereof, and shall communicate with the Loss and Salvage Organization, if any, now or hereafter designated by the Contracting Officer, and with the assistance of the Loss and Salvage Organization so designated (unless the Contracting Officer has designated that no such organization be employed), shall take all reasonable

steps to protect the Government Property from further damage, separate the damaged and undamaged Government Property, put all the Government Property in the best possible order, and furnish to the Contracting Officer a statement of

(i) the lost, destroyed, and damaged Government Property,

(ii) the time and origin of the loss, destruction, or damage,

(iii) all known interests in commingled property of which the Government Property is a part, and

(iv) the insurance, if any, covering any part of or interest in such commingled property.

The Contractor shall make repairs and renovations of the damaged Government Property or take such other action as the Contracting Officer directs.

(4) In the event the Contractor is indemnified, reimbursed, or otherwise compensated for any loss or destruction of or damage to the Government Property, he shall use the proceeds to repair, renovate, or replace the Government Property involved, or shall credit such proceeds against the cost of the work covered by the contract, or shall otherwise reimburse the Government, as directed by the Contracting Officer. The Contractor shall do nothing to prejudice the Government's right to recover against third parties for any such loss, destruction, or damage and, upon the request of the Contracting Officer, shall, at the Government's expense, furnish to the Government all reasonable assistance and cooperation (including the prosecution of suit and the execution of instruments of assignment in favor of the Government) in obtaining recovery. In addition, where the subcontractor has not been relieved from liability for any loss or destruction of or damage to Government Property, the Contractor shall enforce the liability of the subcontractor for such loss or destruction of or damage to the Government Property for the benefit of the

Government.

*(5) If this contract is for the development, production, modification, maintenance, or overhaul of aircraft, or otherwise involves the furnishing of aircraft by the Government, the clause of this contract entitled "Flight Risks" shall control, to the extent it is applicable, in the case of loss or destruction of, or damage to, aircraft.

(g) The Government shall at all reasonable times have access to the premises where any of the Government Property is located.

(h) The Government Property shall remain in the possession of the Contractor for such period of time as is required for the

*This subparagraph may be omitted where it is clearly inapplicable and shall be deleted when the Flight Risks clause is omitted.

performance of this contract unless the Contracting Officer determines that the interests of the Government require removal of such property. In such case the Contractor shall promptly take such action as the Contracting Officer may direct with respect to the removal and shipping of Government Property. In any such instance, the contract may be amended to accomplish an equitable adjustment in the terms and provisions thereof.

(1) Upon the completion of this contract, or at such earlier dates as may be fixed by the Contracting Officer, the Contractor shall submit to the Contracting Officer in a form acceptable to him, inventory schedules covering all items of the Government Property not consumed in the performance of this contract, or not theretofore delivered to the Government, and shall deliver or make such other disposal of such Government Property as may be directed or authorized by the Contracting Officer. The net proceeds of any such disposal shall be credited to the cost of the work covered by the contract or shall be paid in such manner as the Contracting Officer may direct. The foregoing provisions shall apply to scrap from Government Property: Provided, however, That the Contracting Officer may authorize or direct the Contractor to omit from such inventory schedules any scrap consisting of faulty castings or forgings, or cutting and processing waste, such as chips, cuttings, borings, turnings, short ends, circles, trimmings, clippings, and remnants, and to dispose of such scrap in accordance with the Contractor's normal practice and account therefor as a part of general overhead or other reimbursable cost in accordance with the Contractor's established accounting procedures.

(1) Unless otherwise provided herein, the Government shall not be under any duty or obligation to restore or rehabilitate, or to pay the costs of the restoration or rehabilitation of, the Contractor's plant or any portion thereof which is affected by the removal of any Government Property.

(k) Directions of the Contracting Officer and communications of the Contractor issued pursuant to this clause shall be in writing.

As provided in paragraph (1) of the above clause, the contracting officer may authorize or approve use of the contractor's established scrap disposal and accounting procedures whenever the amount and recoverable value of scrap from the Government property are relatively minor and the contractor's established procedures for accumulating and disposing of scrap and crediting the proceeds thereof to general overhead or other general cost will permit the Government to share equitably in such scrap recovery

through a reduction of overhead or other cost factor affecting reimbursement under the contract.

§ 18-13.504 Special tooling clause for fixed-price contracts.

The following clause shall be used in fixed-price contracts for supplies or services for the performance of which the contractor furnishes special tooling, under the conditions set forth in § 18– 13.302(b), but is not for use in contracts in which special tooling is called. for as a separate end item in the Schedule (see § 18-13.302(a)).

SPECIAL TOOLING (APRIL 1962)

(a) The term "special tooling," as used in this clause, means all jigs, dies, fixtures, molds, patterns, special taps, special gauges, special test equipment, other special equipment and manufacturing aids, and replacements thereof, acquired or manufactured by the Contractor for use in the performance of this contract, which are of such a specialized nature that, without substantial modification or alteration, their use is limited to the production of such supplies or parts thereof, or the performance of such services, as are peculiar to the needs of the Government. The term does not include (1) items of tooling or equipment heretofore acquired by the Contractor, or replacements thereof, whether or not altered or adapted for use in the performance of this contract; (ii) consumable small tools; or (iii) general or special machine tools, or similar capital items.

(b) The Contractor agrees not to use any items of special tooling except in the performance of this contract, or except as otherwise provided by this clause, without prior written approval of the Contracting Officer. The Contractor may, with the approval of the Contracting Officer, use the special tooling in the performance of other contracts with the Government, or subcontracts under Government contracts: Provided, That the Contractor agrees not to include in the price or prices for any such contracts or subcontracts, involving the use of such special tooling, the cost of such tooling or any allowance or charge to cover depreciation or amortization which has previously been charged against this contract.

(c) Within 60 days after delivery of the first-production end items under this contract, or such later date as may be prescribed by the Contracting Officer, the Contractor shall, if the Contracting Officer so requests, furnish the Contracting Officer a list of all special tooling acquired or manufactured by the Contractor for use in the performance of this contract. The list shall specify the nomenclature, tool number and related product part number or service, and unit or group cost of the special tooling. Upon

completion or termination of all or a substantial part of the work under this contract the Contractor shall furnish a final list in the same form covering all items not previously reported under this paragraph: Provided, however, That the Contracting Officer may by written notice waive this requirement or extend it until the completion of this contract and other contracts and subcontracts as to which approval has been obtained under paragraph (b) above. Special tooling which has become obsolete as a result of changes in design or specifications need not be reported, except as provided for in paragraph (d).

(d) In the event of any changes in design or specifications which affect interchangeability of parts, the Contractor shall, unless otherwise agreed to by the Contracting Officer, give the Contracting Officer notice of any part which is not interchangeable with the new or superseding part, and the usable special tooling for each part covered in such notice shall be retained by the Contractor subject to the provisions of paragraph (1), pending disposition under paragraph (f).

(e) At the time he furnishes any list or notice under (c) or (d) above, the Contractor may designate those items of special tooling (either specifically or by listing the particular products, parts, or services for which such items were used or designed) which he desires to retain, together with a written offer (i) to retain any or all of such items, free and clear of any Government interest, for an amount designated therein, which should ordinarily not be less than the then fair value of such items (which fair value takes into account, among other things, the value of such items to the Contractor for use in further work by him); or (ii) to retain any or all such items for such period of time and subject to such terms and conditions as may be agreed to by the parties hereto, subject to ultimate retention or disposition of such items in accordance with paragraph (f) hereof.

(f) Within 90 days after receipt of any list or notice under paragraph (c) or (d) hereof, or such further period as may be agreed upon by the parties, the Contracting Officer shall furnish to the Contractor (i) a list specifying the particular products, parts or services for which the Government may require special tooling, together with a request that the Contractor transfer title (to the extent not previously transferred under any other clause of this contract) and deliver to the Government all usable items of special tooling which were used or designed for the manufacture or performance of any designated portion of such products, parts, or services, and which were on hand when production of such products or parts, or performance of such services, ceased; or (ii) an acceptance or rejection of any offer made by the Contractor under paragraph (e)