3. SAME.

A. contracted to sell to B. 5,000 tons of rails, to be shipped at the rate of about 1,000 tons per month, the whole to be shipped within six months, each cargo to be paid for on delivery. A. shipped but 350 tons the first month, and 897 the second month, but shipped the whole within the six months. B., after having received and paid for one cargo, learned of the default of A. as to the first month's shipment. Held, that he could rescind the contract, and refuse to accept the other shipments.

Motion to take off Nonsuit.

Assumpsit by A. Norrington & Co. against Peter Wright & Sons upon the following contract:

“PHILADELPHIA, January 19, 1880. "Sold to Messrs. Peter Wright & Sons, for account of Messrs. A. Norrington & Co., London, 5,000 tons old T iron rails, for shipment from a European port or ports, at the rate of about 1,000 tons per month, beginning February, 1880, but whole contract to be shipped before August 1, 1880, at $45 per ton of 2,240 pounds, custom-house weight, ex ship Philadelphia. Settlement cash, on presentation of bills accompanied by custom-house certificate of weight. Sellers to notify buyers of shipments, with vessels named, as soon as known by them. Sellers not to be compelled to replace any parcel lost after shipment. Sellers, when possible, to secure to buyers right to name discharging berth of vessels at Philadelphia.

[ocr errors]

The declaration averred performance by plaintiffs, and refusal to accept by defendants.

At the trial, (before McKennan and Butler, JJ.,) plaintiffs proved shipments under this contract as follows: February, 395 tons; March, 897 tons; April, 1,349 tons; May, 1,099 tons; June, 991 tons; July, 306 tons. The first cargo, con-, sisting of the 395 tons shipped in February, was received and paid for by defendants. Upon the arrival of the other cargoes, defendants declined to receive them, and claimed the right to rescind the contract, because of the failure of plaintiffs to ship the stipulated quantity in February and March. Plaintiffs failed to show that defendants, at the time of receiving the first cargo, knew of plaintiffs' default in making the shipments.

v.5, no.9-49

At the close of plaintiffs' evidence, the court being of opinion that defendants had the right to rescind the contract, plaintiffs elected to suffer a nonsuit, with leave to move to take it off.

Samuel Dickson and John C. Bullitt, for the motion.

As the contract expressly allowed six months for the shipment of the whole 5,000 tons, the failure to ship 1,000 tons in any one month was immaterial. The facts that each shipment was to be paid for separately, that the time of arrival was uncertain, and that lost shipments were not to be replaced, all show that the contract was severable. The rule is that if the part to be performed by one party consists of several and distinct items, and the price to be paid by the other is apportioned to each item, the contract is severable. 2 Parsons on Contracts, 29-31; Lucesco Oil Co. v. Brewer, 66 Pa. St. 351; Graves v. Scott, 80 Pa. St. 88; Scott v. Kittanning Coal Co. 89 Pa. St. 231; note to same case, 19 Am. Law Reg. (N. S.) 418; Morgan v. McKee, 77 Pa. St. 229; Perkins v. Hart, 11 Wheat. 237. If the contract is severable under the rule of Pordage v. Cole, 1 Wms. Saund. 320, the covenant is substituted for exact performance, and the failure of the seller to supply the first monthly instalment does not entitle the purchaser to rescind unless such failure is accompanied by other circumstances showing an intention to abandon the contract. Benjamin on Sales, § 426; Stoddart v. Smith, 5 Burn. 355; Tipton v. Feitner, 20 N. Y. 423; Snook v. Fries, 19 Barb. 313; Lee v. Beebe, 13 Hun. 89; Johnassohn v. Young, 4 B. & S. 296 (116 E. C. L.;) Simpson v. Crippen, Law Rep. 8 Q. B. 14; Roper v. Johnson, L. R. 8 C. P. Div. 167; Freeth v. Burr, L. R. 9 C. P. 208; Bloomer v. Berntine, L. R. 9 C. P. 588; Ex parte Chalmers, L. R. 9 C. P. 289; Morgan v. Bain, L. R. 10 C. P. 15; Houck v. Muller, London Times, Dec. 18, 1880.

R. C. McMurtrie, contra.

The rule adopted in the English cases cited by plaintiffs is a departure from the earlier decisions of the English courts, and is inconsistent with other recent English decisions. Johnson v. Johnson, 3 B. & Pull. 162-70; Oxendale v. Weth

erill, 9 B & Cr. 387; Hoare v. Rennie, 5 H. & Norm. 19; Bradford v. Williams, L. R. 7 Exch. 261; Coddington v. Paleslogo, L. R. 2 Exch. 193. It has not been adopted in this country. Smith v. Lewis, 40 Ind. 98; McMillan v. Vanderslip, 12 John. 165; Catlin v. Tobias, 26 N. Y. 217; Shinn v. Bodine, 60 Pa. St. 182; Raybold v. Williams, 30 Pa. St. 268; Bradley v. King, 44 Ill. 339. When a time is fixed for delivery, a rescission is always allowed upon failure to deliver, and no intention to vary this can be drawn from the agreement for successive shipments of the one subject of sale. If the contract still remains one, though divisible in performance, there is no reason why this right of rescission should not be exercised.

Partial performance by the vendor does not prevent the vendee from rescinding if the contract furnishes an exact measure of compensation for the benefit received. Chitty on Cont. 1094; Hill v. Crew, 1 Metc. 268-72; Haines v. Tucker, 50 N. H. 309; Dwinel v. Harvard, 30 Me. 258; Miner v. Bradley, 22 Pick. 459; Bradley v. King, 44 Ill. 339; Catlin v. Tobias, 26 N. Y. 217; Sharp v. The Turnpike, 3 Pa. St.

BUTLER, D. J., (orally.) To justify an allowance of the motion, we must be convinced that our ruling at the trial was wrong. We are not so convinced. The motion must therefore, be dismissed. For myself, however, I may say that I regard the point as involved in serious doubt,-not so much when considered on general principles, as when viewed in the light of modern decisions. The right to rescind a contract for non-performance, is a remedy as old as the law of contract itself. Where the contract is entire,-indivisible,-the right is unquestioned. The undertakings on the one side, and on the other, are dependent, and performance by one party cannot be enforced by the other, without performance, or a tender of performance, on his own part. In the case before us the contract is "severable." But to say it is "severable,' does not advance the plaintiffs' argument. A "severable" contract, as the language imports, is a contract liable simply to be severed. In its origin, and till severed, it is entire-a single bargain, or transaction. The doctrine of severableness, (if I may be allowed to coin a word,) in contracts, is an invention of the courts, in the interest of justice, designed to

[ocr errors]

enable one who has partially performed, and is entitled on such partial performance, to something from the other side, to sustain an action, in advance of complete performance,as where goods are sold to be delivered and paid for in parcels, to enable the seller to recover for the parcels delivered, in advance of completing his undertaking. But this equitable doctrine should not be invoked by one who has failed to perform, for the purpose of defeating the other's right to rescind, and thus to protect himself against the consequences of his own wrong. As against such a party the contract should be treated, and enforced, as entire. To say therefore that the contract is "severable," does not, I repeat, advance the argument. To render the plaintiff's position logical, it is necessary to take a step forward, and hold that such a transaction, (it would not be accurate in this view to call it a contract,) constitutes several distinct, independent contracts. Then of course it follows that a failure as respects one of several successive deliveries, affords no right to rescind in regard to those yet to be made. And this step, after much apparent doubt and hesitation, the English courts have taken. It was the necessary outgrowth of the decision in Simpson v. Crippen, which overruled Hoare v. Rennie. In our own country the cases are inharmonious, and the question unsettled. After a careful examination of what has been said on the subject, I shall not be surprised if the courts here finally adopt the present English rule, and thus substitute compensation in damages for the remedy by rescission, to the extent there done. I say this, however, not because I think it wise to adopt this rule, but because of an apparent leaning in that direction. The question, however, as here presented, is properly for the supreme court, to which I hope it may be carried, and the rule thus be settled.

MCKENNAN, C. J., (orally.) I concur in the foregoing decision. I am not satisfied that the weight of authority in this country is preponderating in favor of following the English rule. I have very great doubt as to the justice of this rule and am not disposed to follow it. I am not willing to take this advanced step.

HAVEMEYER v. WRIGHT.*

(Circuit Court, E. D. Pennsylvania. January 24, 1881.)

1. SEVERABLE CONTRACT-TENDER OF PART PERFORMANCE-REFUSAL TO ACCEPT-AFFIDAVIT OF DEFENCE.

A. contracted to deliver to B. 700 tons of rails, to be shipped from Europe, in February, in one or more vessels, each cargo to be paid for on delivery. A. shipped one cargo of 342 tons, which arrived in May, but B. refused to accept it. In a suit brought by A. against him, B. filed an affidavit of defence setting forth that A. had not shipped the residue at the time he tendered the first cargo, and had never intended to ship them. Held, a sufficient defence.

Rule for judgment for want of a sufficient affidavit of defence.

This was an action of assumpsit by Havemeyer & Vigelius against Peter Wright & Sons. Plaintiffs filed a copy of the following contract:

GEORGE A. BOYNTON.

"70 WALL STREET,

"NEW YORK, Jan. 20th, 1880. "Sold for account of Messrs. Havemeyer & Vigelius seven hundred (700) tons old T iron rails, (5 per cent., more or less, seller's option,) for shipment from Europe to Philadelphia in February, 1880, and for delivery, ex vessel or vessels, on wharf in port of Philadelphia; price forty-three and one-half dollars ($43.50) per ton of 2,240 pounds; U. S. custom house weights to decide quantity. Terms: Spot cash, on presentation of invoice, with U. S. certificate of weight for each lot. Name of vessel to be given to buyers as soon as known to sellers. "GEO. A. BOYNTON,

"Accepted.

"Broker.

"Per GEO. H. WRIGHT.

“PETER WRIGHT & SONS. Per M."

With the above was filed a copy of invoice presented to defendants June 7, 1880, for 342 700-2240 tons at $43.50,$14,890.59,-with United States certificate of weight; imported in ship Livingston, which arrived May 8, 1880.

*Reported by Frank P. Prichard, Esq., of the Philadelphia bar.