shall approve all substitutions of subcontractors before bid opening and during contract performance, in order to ensure that the substitute firms are eligible MBES.

(3) Recipients covered by the disadvantaged business program requirements of subpart D of this part shall, in determining whether a firm is an eligible disadvantaged business enterprise, take at least the following steps:

(i) Perform an on-site visit to the offices of the firm and to any job sites on which the firm is working at the time of the eligibility investigation;

(ii) Obtain the resumes or work histories of the principal owners of the firm and personally interview these individuals;

(iii) Analyze the ownership of stock in the firm, if it is a corporation;

(iv) Analyze the bonding and financial capacity of the firm;

(v) Determine the work history of the firm, including contracts it has received and work it has completed;

(vi) Obtain or compile a list of equipment owned or available to the firm and the licenses of the firm and its key personnel to perform the work it seeks to do as part of the DBE program; and

(vii) Obtain a statement from the firm of the type of work it prefers to perform as part of the DBE program. (g) Percentage goals for the dollar value of work to be awarded to MBES. (1) Once the recipient has reviewed proposed contracting to identify those Contracting activities which have the greatest potential for MBE participation, the recipient shall set goals that are practical and related to the potential availability of MBES in desired areas of expertise.

(2) The applicant/recipient shall establish two types of MBE goals:

(i) Overall goals for its entire MBE program, for a specified period of time (e.g. one year), or for a specific project, (e.g. the construction of a facility); and

(ii) Contract goals on each specific prime contract with subcontracting possibilities, which the bidder or proposer must meet or exceed or demonstrate that it could not meet despite its best efforts.

(3)(i) Recipients shall submit their overall goals and a description of the methodology used in establishing them with their MBE program. When the overall goals expire, new overall goals shall be set and submitted to the Department for approval. Contract goals need not be submitted in the applicant's MBE program, but the program shall contain a description of the methodology to be used in establishing them. Contract goals may require approval by the Department prior to contract solicitation.

(ii) At the time the recipient submits its overall goals to the Department for approval, the recipient shall publish a notice announcing these goals, informing the public that the goals and a description of how they were selected are available for inspection during normal business hours at the principal office of the recipient for 30 days following the date of the notice, and informing the public that the Department and the recipient will accept comments on the goals for 45 days from the date of the notice. The notice shall include addresses to which comments may be sent, and shall be published in general circulation media and available minority-focus media and trade association publications, and shall state that the comments are for informational purposes only.

(4) Recipients covered by the disadvantaged business enterprise program requirements of subpart D of this part shall establish an overall goal and contract goal for firms owned and controlled by socially and economically disadvantaged individuals. Other recipients shall establish separate overall and contract goals for firms owned and controlled by minorities and firms owned and controlled by women, respectively.

(5) The applicant shall consider the following factors in setting overall goals:

(i) Overall goals shall be based on projection of the number and types of contracts to be awarded by the applicant and a projection of the number and types of MBES likely to be available to compete for contracts from the recipient over the period during which the goals will be in effect.

(ii) Overall goals shall also be based on past results of the applicant's/recipient's efforts to contract with MBES and the reasons for the high or low level of those results.

(6) The applicant/recipient shall review the overall goals at least annually. The review process shall analyze projected versus actual MBE participation during the previous year. The necessary revisions shall be made based on the analysis and submitted to the Department for approval.

(7) Goals shall be set for specific contracts based on the known availability of qualified MBES.

(8) Recipients and contractors shall, at a minimum, seek MBES in the same geographic area in which they seek contractors or subcontractors generally for a given solicitation. If the recipient or contractor cannot meet the goals using MBES from this geographic area, the recipient or contractor, as part of its efforts to meet the goal, shall expand its search to a reasonable wider geographic area.

(h) A means to ensure that competitors make good faith efforts to meet MBE contract goals. (1) For all contracts for which contract goals have been established, the recipient shall, in the solicitation, inform competitors that the apparent successful competitor will be required to submit MBE participation information to the recipient and that the award of the contract will be conditioned upon satisfaction of the requirements established by the recipient pursuant to this subsection.

(i) The apparent successful competitor's submission shall include the following information:

(A) The names and addresses of MBE firms that will participate in the contract;

(B) A description of the work each named MBE firm will perform;

(C) The dollar amount of participation by each named MBE firm.

(ii) The recipient may select the time at which it requires MBE information to be submitted. Provided, that the time of submission shall be before the recipient commits itself to the performance of the contract by the apparent successful competitor.

(2) If the MBE participation submitted in response to paragraph (h)(1) of this section does not meet the MBE contract goals, the apparent successful competitor shall satisfy the recipient that the competitor has made good faith efforts to meet the goals.

(i) The recipient may prescribe other requirements of equal or greater effectiveness in lieu of good faith efforts. Any recipient choosing alternative requirements shall inform the DOT office concerned by letter of the content of the requirements it has prescribed within 30 days of the effective date of this subsection. The recipient may put these alternative requirements into effect immediately and prior DOT approval of alternative requirements is not necessary.

(ii) If the Department determines that the alternative requirements are not as or more effective than the good faith efforts provisions of this subsection, the Department may require the recipient to use the good faith efforts requirements of this subsection instead of the requirements it has prescribed.

(3) Meeting MBE contract goals, making good faith efforts as provided in paragraph (h)(2) of this section, or meeting requirements established by recipients in lieu of good faith efforts, is a condition of receiving a DOT-assisted contract for which contract goals have been established.

(i) [Reserved]

(j) A description of the methods by which the recipient will require subrecipients, contractors, and subcontractors to comply with applicable MBE requirements. (1) The recipient shall include in its MBE program a description and the specific language of any preconditions to subgrants or contracts pertaining to the use of MBES, including subcontracting programs, it awards with DOT funds in addition to those required by this section. It shall specify on what size and/or type of contracts and subgrants it includes such preconditions. The description shall contain a summary of the ways the recipient provides help to its subrecipients, contractors, and subcontractors in drafting and implementing their programs for using MBES. The description shall also include the

means by which the recipient enforces the requirements placed on subrecipients, contractors and subcontractors.

(2) Any MBE subcontracting programs required by the recipient in addition to those required by this section shall be submitted to the recipient by the apparent successful bidder/proposer. The bidders/proposers shall be advised in the solicitation that failure to submit the additional MBE subcontracting program shall make the bidder/proposer ineligible for award.

(k) Procedures by which the applicant/recipient will implement MBE set-asides. Where not prohibited by state or local law and determined by the recipient to be necessary to meet MBE goals, procedures to implement MBE set-asides shall be established. MBE set-asides shall be used only in cases where at least three MBES with capabilities consistent with contract requirements exist so as to permit competition.

APPENDIX A TO § 23.45—GUIDANCE
CONCERNING GOOD FAITH EFFORTS

To determine whether a competitor that has failed to meet MBE contract goals may receive the contract, the recipient must decide whether the efforts the competitor made to obtain MBE participation were "good faith efforts” to meet the goals. Efforts that are merely pro forma are not good faith efforts to meet the goals. Efforts to obtain MBE participation are not good faith efforts to meet the goals, even if they are sincerely motivated, if, given all relevant circumstances, they could not reasonably be expected to produce a level of MBE participation sufficient to meet the goals. In order to award a contract to a competitor that has failed to meet MBE contract goals, the recipient must determine that the competitor's efforts were those that, given all relevant circumstances, a competitor actively and aggressively seeking to meet the goals would make.

To assist recipients in making the required judgment, the Department has prepared a list of the kinds of efforts that contractors may make in obtaining MBE participation. It is not intended to be a mandatory checklist; the Department does not require recipients to insist that a contractor do any one, or any particular combination, of the things on the list. Nor is the list intended to be exclusive or exhaustive. Other factors or types of efforts may be relevant in appropriate cases. In determining whether a contractor has made good faith efforts, it will usually be important for a recipient

to look not only at the different kinds of efforts that the contractor has made, but also the quantity and intensity of these efforts.

The Department offers the following list of kinds of efforts that recipients may consider:

(1) Whether the contractor attended any pre-solicitation or pre-bid meetings that were scheduled by the recipient to inform MBES of contracting and subcontracting opportunities;

(2) Whether the contractor advertised in general circulation, trade association, and minority-focus media concerning the subcontracting opportunities;

(3) Whether the contractor provided written notice to a reasonable number of specific MBES that their interest in the contract was being solicited, in sufficient time to allow the MBEs to participate effectively;

(4) Whether the contractor followed up initial solicitations of interest by contacting MBES to determine with certainty whether the MBES were interested;

(5) Whether the contractor selected portions of the work to be performed by MBES in order to increase the likelihood of meeting the MBE goals (including, where appropriate, breaking down contracts into economically feasible units to facilitate MBE participation);

(6) Whether the contractor provided interested MBES with adequate information about the plans, specifications and requirements of the contract;

(7) Whether the contractor negotiated in good faith with interested MBES, not rejecting MBES as unqualified without sound reasons based on a thorough investigation of their capabilities;

(8) Whether the contractor made efforts to assist interested MBEs in obtaining bonding, lines of credit, or insurance required by the recipient or contractor; and

(9) Whether the contractor effectively used the services of available minority community organizations; minority contractors' groups; local, state and Federal minority business assistance offices; and other organizations that provide assistance in the recruitment and placement of MBES.

(Title VI of the Civil Rights Act of 1964; sec. 30 of the Airport and Airway Development Act of 1970, as amended; sec. 905 of the Railroad Revitalization and Regulatory Reform Act of 1976; sec. 19 of the Urban Mass Transportation Act of 1964, as amended; 23 U.S.C. 324; E.O. 11625; E.O. 12138)

[45 FR 21184, Mar. 31, 1980, as amended at 46 FR 23461, Apr. 27, 1981; 52 FR 39230, Oct. 21, 1987]

(c) Under the following circumstances, a business seeking to participate as an MBE under this subpart need not submit schedule A or B:

(1) If a DOT recipient has established a different certification process that DOT has determined to be as or more effective than the process provided for by this section. Where such a process exists, potential MBE contractors shall submit the information required by the recipient's process.

(2) If the potential MBE contractor states in writing that it has submitted the same information to or has been certified by the DOT recipient involved, any DOT element, or another Federal agency that uses essentially the same definition and ownership and control criteria as DOT. The potential MBE contractor shall obtain the information and certification (if any) from the other agency and submit it to the recipient or cause the other agency to submit it. The recipient may rely upon such a certification. Where another agency has collected information but not made a determination concerning eligibility, the DOT recipient shall make its own determination based on the information it has obtained from the other agency.

(3) If the potential MBE contractor has been determined by the Small Business Administration to be owned and controlled by socially and economically disadvantaged individuals under section 8(a) of the Small Business Act, as amended.

§ 23.53 Eligibility standards.

(a) The following standards shall be used by recipients in determining whether a firm is owned and controlled by one or more minorities or women is and shall therefore be eligible to be certified as an MBE. Businesses aggrieved by the determination may appeal in accordance with procedures set forth in § 23.55.

(1) Bona fide minority group membership shall be established on the basis of the individual's claim that he or she is a member of a minority group and is so regarded by that particular minority community. However, the recipient is not required to accept this I claim if it determines the claim to be invalid.

(2) An eligible minority business enterprise under this part shall be an independent business. The ownership and control by minorities or women shall be real, substantial, and continuing and shall go beyond the pro forma ownership of the firm as reflected in its ownership documents. The minority or women owners shall enjoy the customary incidents of ownership and shall share in the risks and profits commensurate with their ownership interests, as demonstrated by a examination of the substance rather than form of arrangements. Recognition of the business as a separate entity for tax or corporate purposes is not necessarily sufficient for recognition as an MBE. In determining whether a potential MBE is an independent business, DOT recipients shall consider all relevant factors, including the date the business was established, the adequacy of its resources for the work of the contract, and the degree to which financial, equipment leasing, and other relationships with nonminority firms vary from industry practice.

(3) The minority or women owners shall also possess the power to direct or cause the direction of the management and policies of the firm and to make the day-to-day as well as major decisions on matters of management, policy, and operations. The firm shall not be subject to any formal or informal restrictions which limit the customary discretion of the minority or women owners. There shall be no restrictions through, for example, bylaw provisions, partnership agreements, or charter requirements for cumulative voting rights or otherwise that prevent the minority or women owners, without the cooperation or vote of any owner who is not a minority or woman, from making a business decision of the firm.

(4) If the owners of the firm who are not minorities or women are disproportionately responsible for the operation of the firm, then the firm is not controlled by minorities or women and shall not be considered an MBE within the meaning of this part. Where the actual management of the firm is contracted out to individuals other than the owner, those persons who have the ultimate power to hire and fire the

[ocr errors][merged small]

(2) The fees charged for delivery of materials and supplies required on a job site (but not the cost of the materials and supplies themselves) when the hauler, trucker, or delivery service is not also the manufacturer of or a regular dealer in the materials and supplies, provided that the fee is determined by the recipient to be reasonable and not excessive as compared with fees customarily allowed for similar services.

(3) The fees or commissions charged for providing any bonds or insurance specifically required for the performance of the contract, provided that the fee or commission is determined by the recipient to be reasonable and not excessive as compared with fees customarily allowed for similar services.

[45 FR 21184, Mar. 31, 1980, as amended at 52 FR 39230, Oct. 21, 1987]

§ 23.49 Maintenance of records and reports.

(a) In order to monitor the progress of its MBE program the applicant/recipient shall develop a recordkeeping system which will identify and assess MBE contract awards, prime contractors' progress in achieving MBE subcontract goals, and other MBE affirmative action efforts.

(b) Specifically, the applicant/recipient shall maintain records showing:

(1) Procedures which have been adopted to comply with the requirements of this part.

(2) Awards to MBEs. These awards shall be measured against projected MBE awards and/or MBE goals. To assist in this effort, the applicant shall obtain regular reports from prime contractors on their progress in meeting contractual MBE obligations.

(3) Specific efforts to identify and award contracts to MBES.

(c) Records shall be available upon the request of an authorized officer or employee of the government.

(d)(1) The recipient shall submit reports conforming in frequency and format to existing contract reporting requirements of the applicable Departmental element. Where no such contract reporting requirements exist, MBE reports shall be submitted quarterly.

(2) These reports shall include as a minimum:

(i) The number of contracts awarded to MBES;

(ii) A description of the general categories of contracts awarded to MBES; (iii) The dollar value of contracts awarded to MBES;

(iv) The percentage of the dollar value of all contracts awarded during this period which were awarded to MBES; and

(v) An indication of whether and the extent of which the percentage met or exceeded the goal specified in the application.

(3) The records and reports required by this section shall provide information relating to firms owned and controlled by minorities separately from information relating to firms owned and controlled by women. If the records and reports include any section 8(a) contractors that are not minorities or women, information concerning these contractors shall also be recorded and reported separately.

§ 23.51 Certification of the eligibility of minority business enterprises.

(a) To ensure that this part benefits only MBES which are owned and controlled in both form and substance by one or more minorities or women, DOT recipients shall use Schedules A and B (reproduced at the end of this part) to certify firms who wish to participate as MBES in DOT under this part.

(b) Except as provided in paragraph (c) of this section, each business, including the MBE partner in a joint venture, wishing to participate as a MBE under this part in a DOT-assisted contract shall complete and submit Schedue A. Each entity wishing to participate as a joint venture MBE under this part in DOT-assisted contracts shall in addition complete and submit Schedule B. The schedule(s) shall be signed and notarized by the authorized representative of the business entity. A business seeking certification as an MBE shall submit the required schedules with its bid or proposal for transmission to the contracting agency involved.